[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111533":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111533,786,2,"多选题","桥头跳车正确的防治措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","台后填土回填压实度达到要求",true,{"key":16,"text":17,"correct":18},"B","减少台前预压长度",false,{"key":20,"text":21,"correct":14},"C","采用砂石料做桥头填料",{"key":23,"text":24,"correct":14},"D","做好桥头路堤的排水、防水工程",{"key":26,"text":27,"correct":14},"E","改善地基性能，提高地基承载力","ACDE","2020版教材P157 保证足够的台前预压长度，连续进行沉降观测。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]