[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111531":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111531,786,2,"多选题","预拱度偏差防治措施正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","提高支架基础、支架及模板的施工质量",true,{"key":16,"text":17,"correct":14},"B","严格控制张拉时的混凝土强度",{"key":19,"text":20,"correct":21},"C","预制梁存梁时间宜长",false,{"key":23,"text":24,"correct":14},"D","及时调整预拱度误差",{"key":26,"text":27,"correct":14},"E","波纹管的安装定位应准确","ABDE","2020版教材P155 预拱度偏差防治措施：（1）提高支架基础、支架及模板的施工质量，确保模板的标高无偏差；（2）加强施工控制，及时调整预拱度误差；（3）严格控制张拉时的混凝土强度，控制张拉的试块应与梁板同条件养护，对于预制梁还需控制混凝土的弹性模量；（4）要严格控制预应力筋在结构中的位置，波纹管的安装定位应准确；控制张拉时的应力值，按要求的时间持荷；（5）张拉千斤顶定期标定，钢绞线伸长值的计算应采用同批钢绞线弹性模量的实测值；（6）预制梁存梁时间不宜过长，控制预制梁与桥面系铺装的龄期差。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]