[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111527":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111527,786,2,"多选题","现浇箱涵施工主要工序（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","砂砾垫层施工",true,{"key":16,"text":17,"correct":14},"B","基础模板安装与混凝土浇筑",{"key":19,"text":20,"correct":21},"C","盖板吊装",false,{"key":23,"text":24,"correct":14},"D","基坑开挖与基础处理",{"key":26,"text":27,"correct":14},"E","拆模与养护","ABDE","2020版教材P151 1.现浇箱涵施工主要工序 基坑开挖与基坑处理→砂砾垫层施工→基础模板安装→基础混凝土浇筑→墙身及顶板混凝土施工→拆除与养护→进出口及附属工程施工→台背填土及加固",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]