[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111525":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111525,786,2,"多选题","关于台背及与路堤间的回填施工要求正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","二级以下公路的路堤与回填的联结部，应按设计要求预留台阶",true,{"key":16,"text":17,"correct":14},"B","台背回填部分的路床宜与路堤路床同步填筑",{"key":19,"text":20,"correct":14},"C","桥台背和锥坡的回填施工宜同步进行",{"key":22,"text":23,"correct":24},"D","台背和涵洞洞身两侧的填土应分层夯实，其压实度不应小于95%",false,{"key":26,"text":27,"correct":24},"E","不得采用石灰土或水泥稳定土回填","ABC","2020版教材P153 透水性材料不足时，可采用石灰土或水泥稳定土回填；台背和涵洞洞身两侧的填土应分层夯实，其压实度不应小于96%。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]