[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111523":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111523,786,2,"多选题","盖板涵（预制吊装）施工主要工序有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","出入口浆砌",true,{"key":16,"text":17,"correct":14},"B","下基础",{"key":19,"text":20,"correct":21},"C","安装管节",false,{"key":23,"text":24,"correct":14},"D","现浇板座",{"key":26,"text":27,"correct":14},"E","墙身施工","ABDE","2020版教材P151 盖板涵（预制吊装）施工主要工序：测量放线→基坑开挖→下基础→墙身施工→现浇板座→吊装盖板→出入口浆砌→防水层施工→涵洞回填及加固。 安装管节是圆管涵或倒虹吸管施工主要工序 。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]