[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111496":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111496,786,2,"多选题","沥青路面的施工中，沥青混凝土半幅施工不能采用热接缝时，应当采用措施有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","假缝",false,{"key":16,"text":17,"correct":14},"B","胀缝",{"key":19,"text":20,"correct":21},"C","人工顺直刨缝",true,{"key":23,"text":24,"correct":21},"D","切缝",{"key":26,"text":27,"correct":14},"E","拉缝","CD","2021\u002F2020版教材P75 半幅施工不能采用热接缝时，采用人工顺直刨缝或切缝。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]