[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111467":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111467,786,2,"多选题","无机结合料稳定基层整形碾压时，以下（ ）施工要求是正确的。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","在直线段整形，平地机由路中心向两侧进行刮平",false,{"key":16,"text":17,"correct":14},"B","在平曲线段整形，平地机由内侧向外侧进行刮平",{"key":19,"text":20,"correct":14},"C","当混合料接近终凝时，用压路机进行碾压",{"key":22,"text":23,"correct":24},"D","碾压时，应重叠1\u002F2轮宽，后轮必须超过两段的接缝处",true,{"key":26,"text":27,"correct":24},"E","采用人工摊铺和整形的稳定土层，先用两轮压路机碾压，再用重型压路机碾压","DE","2021\u002F2020版教材P59 （1）混合料拌合均匀后，应及时用平地机初步整形。（9） 整形后，混合料的含水率满足要求时，应立即对结构层进行全宽碾压。在直线段 和不设超高的平曲线段，宜从两侧路肩向路中心碾压，且轮迹应重叠1\u002F2 轮宽，后轮应超过两段的接缝处。 （11） 采用人工摊铺和整形的稳定材料层，宜先用拖拉机或 6-8t 两轮压路机或轮胎压路机碾压1-2遍，再用重型压路机碾压。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]