[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111463":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111463,786,2,"多选题","石灰稳定土底基层裂缝的预防措施有（）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","石灰土成型后应及时洒水",true,{"key":16,"text":17,"correct":14},"B","加强剂量控制，使石灰剂量准确",{"key":19,"text":20,"correct":14},"C","施工用土中适量掺加粉煤灰",{"key":22,"text":23,"correct":24},"D","在石灰土层中设置伸缩缝",false,{"key":26,"text":27,"correct":24},"E","含水量提高2个百分点","ABC","2021\u002F2020版教材P98 该题主要考察的是预制构件的吊装， （1）石灰土成型后应及时洒水或覆盖塑料薄膜养护，或铺上一层素土覆盖；（2）选用塑性指数合适的土，或适量掺入砂性土、粉煤灰和其他粒料，改善施工用土的土质；（3）加强剂量控制，使石灰剂量准确，保证拌和遍数和石灰土的均勻性;（4）控制压实含水量，在较大含水量下压实的石灰土，具有较大的干裂，宜在最佳含水量±1%时压实；（5）尽量避免在不利季节施工，最好在第一次冰冻来临一个半月前结束施工。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]