[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111428":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111428,786,2,"多选题","填方施工中，（ ）不宜在雨期施工。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重黏土",true,{"key":16,"text":17,"correct":14},"B","膨胀土",{"key":19,"text":20,"correct":21},"C","砂类土",false,{"key":23,"text":24,"correct":21},"D","路堑的弃方地段",{"key":26,"text":27,"correct":14},"E","盐渍土","ABE","2021\u002F2020版教材P11 重黏土、膨胀土及盐渍土地段不宜在雨期施工。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]