[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111419":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111419,786,2,"多选题","雨期开挖路堑时要注意的事项有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挖方边坡不宜一次挖到设计坡面，应预留一定厚度的覆盖层，待雨期过后再修整到设计坡面。",true,{"key":16,"text":17,"correct":18},"B","开挖土质路堑宜分层开挖，每挖两层均应设置排水横坡",false,{"key":20,"text":21,"correct":18},"C","开挖土质路堑宜分层开挖，每挖两层均应设置排水纵坡",{"key":23,"text":24,"correct":14},"D","开挖土质路堑宜分层开挖，每挖一层均应设置纵横排水坡",{"key":26,"text":27,"correct":14},"E","雨期开挖岩石路堑，炮眼宜水平设置","ADE","2021\u002F2020版教材P11 雨期开挖路堑 （1）雨期路堑施工宜分层开挖，每挖一层均应设置纵横排水坡，使水排放畅通。 （2）挖方边坡不宜一次挖到设计坡面。应预留一定厚度的覆盖层，待雨期过后再修整到设计坡面。 （3）雨期开挖路堑，当挖至路床顶面以上300—500mm时应停止开挖，并在两侧挖好临时排水沟，待雨期过后再施工。 （4）雨期开挖岩石路基，炮眼宜水平设置。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]