[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111405":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111405,786,2,"多选题","洞式渗沟施工时要求采取的措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","洞式渗沟填料顶面宜高于地下水位",true,{"key":16,"text":17,"correct":18},"B","洞式渗沟填料顶面宜低于地下水位",false,{"key":20,"text":21,"correct":14},"C","顶部必须设置封闭层，厚度应大于500mm",{"key":23,"text":24,"correct":18},"D","顶部必须设置封闭层，厚度应大于300mm",{"key":26,"text":27,"correct":18},"E","顶部不需设置封闭层","AC","2021\u002F2020版教材P14 洞式渗沟适用于地下水流量较大的地段。洞式渗沟填料顶面宜高于地下水位。洞式渗沟顶部必须设置封闭层，厚度应大于500mm。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]