[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111386":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111386,786,2,"多选题","关于原地基处理要求正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","原地面为坑，洞，穴等，应在清除沉积物后，用合格填料分层回填，分层压实，压实度符合规定",true,{"key":16,"text":17,"correct":14},"B","地面横坡缓于1:5时，清除地表草皮、腐殖土后，可直接在天然地面上填筑路堤",{"key":19,"text":20,"correct":21},"C","地面横坡为1:5-1:2.5时，原地面应挖台阶，台阶宽度不应小于3m",false,{"key":23,"text":24,"correct":14},"D","应将地基表层碾压密实",{"key":26,"text":27,"correct":21},"E","如对地基表层土进行超挖、分层回填压实，其处理深度小于重型汽车荷载作用的工作区深度","ABD","2021\u002F2020版教材P2 地面横坡为1:5-1：2.5时，原地面应挖台阶，台阶宽度不应小于2m，故C错。如对地基表层土进行超挖、分层回填压实，其处理深度不应小于重型汽车荷载作用的工作区深度。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]