[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111380":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111380,786,2,"多选题","粒料桩的施工工艺程序有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","振冲器就位对中",true,{"key":16,"text":17,"correct":14},"B","清孔",{"key":19,"text":20,"correct":14},"C","关机停水",{"key":22,"text":23,"correct":14},"D","加料振密",{"key":25,"text":26,"correct":27},"E","强制搅拌",false,"ABCD","2021\u002F2020版教材P22 粒料桩的施工工艺程序：整平地面→振冲器就位对中→成孔→清孔→加料振密→关机停水→振冲器移位的施工工艺程序进行。强制搅拌是旋喷桩的施工工艺。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]