[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111341":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111341,786,2,"多选题","沿河路基抢修工程常采用抛石，关于它的说法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","抛石防护除特殊情况外，宜在枯水季节施工",true,{"key":16,"text":17,"correct":14},"B","坡度应不陡于抛石石料浸水后的天然休止角",{"key":19,"text":20,"correct":14},"C","石料粒径应大于300mm",{"key":22,"text":23,"correct":14},"D","抛石体边坡坡度和石料粒径应根据水深、流速和波浪情况确定",{"key":25,"text":26,"correct":27},"E","抛石厚度，宜为粒径的3~4倍；用大粒径时，不得小于3倍",false,"ABCD","2021\u002F2020版教材P32 抛石体边坡坡度和石料粒径应根据水深、流速和波浪情况确定，石料粒径应大于300mm，宜用大小不同的石块掺杂抛投。坡度应不陡于抛石石料浸水后的天然休止角 （2）抛石厚度，宜为粒径的3~4倍；用大粒径时，不得小于2倍。 （3）抛石石料应选用质地坚硬、耐冻且不易风化崩解的石块。 （4）抛石防护除特殊情况外，宜在枯水季节施工",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]