[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111309,786,2,"多选题","对专项风险等级在Ⅲ级及以上的施工，应明确重大风险源的（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","监测",true,{"key":16,"text":17,"correct":14},"B","控制",{"key":19,"text":20,"correct":14},"C","预警措施",{"key":22,"text":23,"correct":14},"D","应急预案",{"key":25,"text":26,"correct":27},"E","评估",false,"ABCD","本题考查的是公路桥梁和隧道工程施工安全风险评估。对专项风险等级在Ⅲ级及以上的施工，应明确重大风险源的监测、控制、预警措施以及应急预案。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]