[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111304":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111304,786,2,"多选题","计日工是指在工程实施过程中，业主有一些临时性的或新增加的项目需要按计日使用人工和（）所需的费用。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料",true,{"key":16,"text":17,"correct":18},"B","延长工期",false,{"key":20,"text":21,"correct":18},"C","风险",{"key":23,"text":24,"correct":18},"D","资金周转",{"key":26,"text":27,"correct":14},"E","施工机械","AE","本题考查的是公路工程工程量清单计价的应用。计日工也称散工或点工，指在工程实施过程中，业主可能有一些临时性的或新增加的项目，而且这种临时的新增项目的工程量在招投标阶段很难估计，希望通过招投标阶段事先定价，避免开工后可能发生时出现的争端，故需要以计日工明细表的方法在工程量清单中予以明确。计日工明细表由总则、计日工劳务、计日工材料、计日工施工机械等方面的内容组成。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]