[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111293":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111293,786,2,"多选题","公路工程进度计划的检查结果可以通过（）体现和分析。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图法",true,{"key":16,"text":17,"correct":18},"B","控制图",false,{"key":20,"text":21,"correct":14},"C","网络计划图",{"key":23,"text":24,"correct":14},"D","S曲线",{"key":26,"text":27,"correct":14},"E","香蕉曲线","ACDE","本题考查的是公路工程进度控制与管理。进度计划检查的方法包括横道图比较法、S形曲线比较法、香蕉形曲线比较法、公路工程进度表、前锋线比较法、完工时点计算法。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]