[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111288":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111288,786,2,"多选题","属于开工准备阶段测量任务的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工控制网建立",true,{"key":16,"text":17,"correct":18},"B","施工控制网复测",false,{"key":20,"text":21,"correct":14},"C","地形地貌复核测量",{"key":23,"text":24,"correct":14},"D","设计控制桩贯通复测",{"key":26,"text":27,"correct":18},"E","安全监控测量","ACD","开工准备阶段测量包括：交接桩、设计控制桩贯通复测、施工控制网建立、地形地貌复核测量。施工阶段测量包括：施工放样测量、工序检查测量、施工控制网复测、沉降位移变形观测及安全监控测量。竣工阶段测量包括：竣工贯通测量和工点竣工测量。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]