[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111270":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111270,786,2,"多选题","桥梁冬季施工时，施工底模板、支架应考虑的荷载包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","汽车荷载",false,{"key":16,"text":17,"correct":18},"B","模板、支架及施工人员、材料、机具的重量",true,{"key":20,"text":21,"correct":14},"C","新浇筑混凝土对侧模板的压力",{"key":23,"text":24,"correct":14},"D","倾倒混凝土时产生的水平荷载",{"key":26,"text":27,"correct":18},"E","可能产生的雪荷载、冬季保温设施荷载","BE","本题考查的是常用模板、支架和拱架的设计。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]