[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111269":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111269,786,2,"多选题","确定套箱围堰的套箱顶标高应考虑（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","浪高",true,{"key":16,"text":17,"correct":18},"B","封底混凝土厚度",false,{"key":20,"text":21,"correct":18},"C","承台高度",{"key":23,"text":24,"correct":18},"D","水的浮力",{"key":26,"text":27,"correct":14},"E","施工期间可能出现的最高水位","AE","本题考查的是承台施工。套箱围堰的平面尺寸应根据承台尺寸、安装及放样误差确定，套箱顶标高应根据施工期间可能出现的最高水位及浪高等因素确定，套箱底板标高根据承台底部标高及封底混凝土厚度确定。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]