[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111264":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111264,786,2,"多选题","关于明挖扩大基础施工的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当坑壁不稳定时，应设挡板支撑，稳定坑壁",true,{"key":16,"text":17,"correct":18},"B","土质较差且有严重流沙现象时，可设集水坑排水",false,{"key":20,"text":21,"correct":14},"C","当基坑为不稳定强风化岩质地基时，可用锚杆挂网喷射混凝土护坡",{"key":23,"text":24,"correct":18},"D","坑壁边缘的挖掘机作业距坑边缘不少0.5m",{"key":26,"text":27,"correct":14},"E","采用简易钢板桩进行基坑支护时，基坑开挖深度不宜大于4m","ACE","本题考查的是明挖扩大基础施工。桥梁基础施工中常用的基坑排水方法中集水坑排水法除严重流砂外，一般情况下均可适用。明挖扩大基础施工，动荷载距坑边缘不小于1.0m；如用机械开挖基坑，挖至坑底时，应保留不小于30cm厚度的底层，在基础浇筑圬工前用人工挖至基底标高。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]