[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111262":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111262,786,2,"多选题","关于先张法预应力筋张拉操作时的施工要点的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","张拉时，同一构件内预应力钢丝、钢绞线不允许出现断丝",false,{"key":16,"text":17,"correct":18},"B","横梁须有足够的刚度，受力后挠度应不大于2mm",true,{"key":20,"text":21,"correct":18},"C","用横梁整批张拉时，千斤顶应对称布置，防止活动横梁倾斜",{"key":23,"text":24,"correct":18},"D","张拉时，工作人员不得站在台座两端或进入台座",{"key":26,"text":27,"correct":18},"E","张拉时，沿台座长度方向每隔4～5m应放一防护架","BCDE","本题考查的是桥梁上部结构装配式施工。张拉时，同一构件内预应力钢丝、钢绞线断丝数量不得超过1%。同时要求预应力钢筋不出现断筋。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]