[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111253":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111253,786,2,"多选题","下列关于悬臂浇筑施工错误的说法（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","0号、1号块的施工一般采用扇形托架浇筑",false,{"key":16,"text":17,"correct":14},"B","临时固结一般采用在支座两侧临时加预应力筋",{"key":19,"text":20,"correct":21},"C","合龙顺序应按设计要求办理，设计无要求时，一般先中跨，后次中跨，再边跨。",true,{"key":23,"text":24,"correct":14},"D","悬臂浇筑混凝土过程中应对桥梁的中轴线、高程进行测量观测和控制",{"key":26,"text":27,"correct":21},"E","悬臂浇筑法解除固结采用动态破碎方法","CE","合龙顺序应按设计要求办理，设计无要求时，一般先边跨，后次中跨，再中跨。多跨一次合龙时，必须同时均衡对称地合龙。合龙时，桥面上设置的所有临时荷载均应与监控单位和设计单位协商决定。临时固结一般采用在支座两侧临时加预应力筋，梁和墩顶之间浇筑临时混凝土垫块。将梁固结在桥墩上，使梁具有一定的抗弯能力。在条件成熟时，再采用静态破碎方法，解除固结。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]