[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111247":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111247,786,2,"多选题","对模板、支架和拱架拆除的技术要求，描述正确的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","模板拆除应按先支先拆，后支后拆的顺序，拆时严禁抛扔",false,{"key":16,"text":17,"correct":14},"B","对预应力混凝土结构，模板应在预应力张拉完成后拆除",{"key":19,"text":20,"correct":21},"C","卸落支架和拱架应在纵向应对称均衡卸落，在横向应同时一起卸落",true,{"key":23,"text":24,"correct":21},"D","简支梁、连续梁宜从跨中向支座依次循环卸落",{"key":26,"text":27,"correct":21},"E","悬臂梁应先卸挂梁及悬臂的支架，再卸无铰跨内的支架。","CDE","模板拆除应按设计的顺序进行，应遵循先支后拆，后支先拆的顺序。对预应力混凝土结构，侧模应在预应力张拉前拆除，底模及支架应在结构建立预应力后拆除。卸落程序时应注意以下几点：（2）满布式拱架卸落时，可从拱顶向拱脚依次循环卸落；（3）简支梁、连续梁宜从跨中向支座依次循环卸落；悬臂梁应先卸挂梁及悬臂的支架，再卸无铰跨内的支架。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]