[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111235":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111235,786,2,"多选题","计算现场拌合工程量时，应考虑（）因素。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","结构层宽度",true,{"key":16,"text":17,"correct":14},"B","结构层厚度",{"key":19,"text":20,"correct":21},"C","运输车辆的吨位",false,{"key":23,"text":24,"correct":21},"D","湿密度",{"key":26,"text":27,"correct":14},"E","干密度","ABE","本题考查的是基层（底基层）混合料生产、摊铺及碾压。根据各路段区级结合料稳定材料层的宽度、厚度及预定的干密度，计算各路段需要的干燥材料的数量。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]