[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111224":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111224,786,2,"多选题","关于水泥稳定土基层路拌法的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","摊铺土之前只需通过计算确定土的松铺系数",false,{"key":16,"text":17,"correct":18},"B","摊铺土应在摊铺水泥的前一天进行",true,{"key":20,"text":21,"correct":18},"C","如已平整的土含水量过小，应在土层上洒水闷料",{"key":23,"text":24,"correct":18},"D","细粒土应经一夜闷料",{"key":26,"text":27,"correct":14},"E","对于二级公路，土与水泥的干拌可采用农用旋耕机作机与平地配合进行","BCD","选项A，摊铺土之前应通过试验确定土的松铺厚度。选项E，对于三、四级公路，在没有专用拌和机械的情况下，可用农用旋转耕作机与多铧犁或平地机相配合进行拌和，但应注意拌和效果，拌和时间不能过长。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]