[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111219":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111219,786,2,"多选题","某二级公路K9+550～K9+600段的路基右侧有一滑坡体，施工单位采取了下列滑坡防治措施，其中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","整平滑坡表面的积水坑，并封堵裂缝",true,{"key":16,"text":17,"correct":14},"B","在滑坡体以外修筑环形截水沟",{"key":19,"text":20,"correct":21},"C","在滑坡体上部堆放砂袋",false,{"key":23,"text":24,"correct":14},"D","修筑抗滑桩进行支挡",{"key":26,"text":27,"correct":14},"E","填方路堤发生的滑坡，可采用反压土方或修建挡土墙等方法处理","ABDE","本题考查的是滑坡地段路基施工。滑坡防治的工程措施主要有排水、力学平衡和改变滑带土三类。当挖方路基上边坡发生的滑坡不大时，可采用刷方（台阶）减重、打桩或修建挡土墙进行处理以达到路基边坡稳定。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]