[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111182,786,1,"单选题","计算某项工序工作持续时间的公式如下：图片1其中D为劳动量，n为生产工作班制数，则R的含义是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时间定额",false,{"key":16,"text":17,"correct":14},"B","产量定额",{"key":19,"text":20,"correct":21},"C","人数或机械台班",true,{"key":23,"text":24,"correct":14},"D","每班工作时间","【考点】公路工程进度计划编制的步骤及内容。 这是确定各施工过程的工种人数、机械规格与数量以及班制选择并确定持续时间时使用的计算方法。本题考核考生是否能记住计算某项工序工作持续时间的公式。记不住也没有很大关系，只要认真分析，题干中给出了n为生产工作班制数，工作班制数只能乘以“台班”。四个选项中只有C选项包含机械台班。所以，本题的正确选项是“C.人数或机械台班”。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]