[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111176,786,1,"单选题","（2018年）根据《公路建设监督管理办法》，政府投资公路建设项目实施的程序包括：①编制可行性研究报告；②编制项目建议书；③编制初步设计文件；④组织项目施工招标；⑤编制施工图设计文件；⑥进行征地拆迁并申报施工许可；⑦办理项目交、竣工验收和财产移交手续；⑧组织项目施工；⑨组织项目后评价。上述实施程序正确的排序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→①→③→④→⑤→⑥→⑧→⑨→⑦",false,{"key":16,"text":17,"correct":18},"B","②→①→③→⑤→④→⑥→⑧→⑦→⑨",true,{"key":20,"text":21,"correct":14},"C","①→②→③→⑤→④→⑥→⑧→⑨→⑦",{"key":23,"text":24,"correct":14},"D","①→②→③→④→⑤→⑥→⑦→⑧→⑨","政府投资公路建设项目的实施顺序：①编制项目建议书；②编制可行性研究报告；③编制初步设计文件；④编制施工图设计文件；⑤组织项目招标；⑥根据国家有关规定，进行征地拆迁等施工前准备工作，并向交通主管部门申报施工许可；⑦根据批准的项目施工许可，组织项目实施；⑧项目完工后，编制竣工图表、工程决算和竣工财务决算，办理项目交、竣工验收和财产移交手续；⑨竣工验收合格后，组织项目后评价。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]