[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111165":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":21},1111165,786,1,"单选题","进度计划编制中，劳动量消耗的均衡性常用不均衡系数来表示，若劳动量消耗最大值为Rmax，最小值为Rmin，均值为 ，则不均衡系数为（ ）。（2017年真题）",[11,14,17,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D","超纲题目，劳动力不均匀系数：K=人力高峰值Rmax\u002F人力平均值。",{"id":6,"name":23,"category":24,"favorite":25},"二建公路工程实务","建筑工程",0]