[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111155,786,1,"单选题","根据《公路工程施工分包管理办法》，分包工程最初的支付申请应由甲在合同约定的时间，向乙报送该阶段施工的付款申请单。上述甲乙分别为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲为分包人、乙为承包人",true,{"key":16,"text":17,"correct":18},"B","甲为承包人、乙为监理",false,{"key":20,"text":21,"correct":18},"C","甲为分包人、乙为监理",{"key":23,"text":24,"correct":18},"D","甲为承包人、乙为业主","分包工程的支付，应由分包人在合同约定的时间，向承包人报送该阶段施工的付款申请单，承包人经过审核后，将其列入施工合同的进度付款申请单内一并提交监理人审批。分包人不能直接向监理人提出支付要求，必须通过承包人。发包人也不能直接向分包人付款，也必须通过承包人。所以，本题的选项是“A“。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]