[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111150,786,1,"单选题","（2019年）施工企业编制公路项目施工成本计划的关键是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","优化施工方案，确定计划工程量",false,{"key":16,"text":17,"correct":18},"B","计算计划成本总降低额和降低率，确定责任目标成本",true,{"key":20,"text":21,"correct":14},"C","依据市场生产要素价格信息，确定施工预算成本",{"key":23,"text":24,"correct":14},"D","施工预算成本与责任目标成本比较，确定计划成本偏差","本题考查的是公路项目施工成本计划的编制。编制施工成本计划的关键是确定责任目标成本，这是成本计划的核心，是成本管理所要达到的目标，成本目标通常以项目成本总降低额和降低率来定量地表示。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]