[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111127,786,1,"单选题","关于施工临时用电的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必须采用TN-S接地、接零保护系统",false,{"key":16,"text":17,"correct":18},"B","必须采用两级配电系统",true,{"key":20,"text":21,"correct":14},"C","分配电箱装设在用电设备或负荷相对集中的区域",{"key":23,"text":24,"correct":14},"D","每台用电设备应有各自专用的开关箱","主要考察的是电气作业安全技术要求，一、公路工程施工现场临时用电的三项基本原则(1)必须采用TN-S接地、接零保护系统；(2)必须采用三级配电系统；(3)必须采用两级漏电保护和两道防线。所以选项“B”错误。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]