[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111107,786,1,"单选题","（2020年真题）在施工过程基本组织方法中，可以科学地利用工作面，实现不同专业队之间平行施工的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","顺序作业法",false,{"key":16,"text":17,"correct":14},"B","平行作业法",{"key":19,"text":20,"correct":21},"C","流水作业法",true,{"key":23,"text":24,"correct":14},"D","平行顺序作业法","P200-204 流水作业法可以科学地利用工作面，实现不同专业作业队之间的平行施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]