[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111105,786,1,"单选题","（2018年）单代号网络图中，箭线一般用来表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作之间的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","一项工作",false,{"key":20,"text":21,"correct":18},"C","一项工作的持续时间",{"key":23,"text":24,"correct":18},"D","工作之间的搭接时距","该试题考点已过期，新版教材已不考，为保证试卷完整性，仅供考生参阅。 单代号网络图中，箭线表示工作间的逻辑关系",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]