[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111103,786,1,"单选题","某路面工程需要突击性施工以尽可能缩短施工工期，最宜采用的施工组织方法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","顺序作业法",false,{"key":16,"text":17,"correct":18},"B","平行作业法",true,{"key":20,"text":21,"correct":14},"C","等节拍流水作业法",{"key":23,"text":24,"correct":14},"D","无节拍流水作业法","公路施工过程基本组织方法有顺序作业法(也称为依次作业法）、平行作业法、流水作业法。其中平行作业法工期最短，但投入的人材机最多，适用于抢工工期的工程。可见选B最符合题意",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]