[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111099,786,1,"单选题","计算劳动量的公式如下：D=Q\u002F C，其中C的含义是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程数量",false,{"key":16,"text":17,"correct":14},"B","时间定额",{"key":19,"text":20,"correct":21},"C","产量定额",true,{"key":23,"text":24,"correct":14},"D","每天班次","所谓劳动量，就是工程细目的工程数量与相应时间定额的乘积，或等于施工时实际使用的工人数量与作业时间的乘积，或实际使用的机械台数与作业时间的乘积。计算劳动量的公式D=Q\u002FC，其中字母含义为：D-劳动量或作业量（工日或台班）；Q-工程数量；C-产量定额。选C",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]