[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111088":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111088,786,1,"单选题","（2019年）关于标线施工技术要求的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","标线工程正式开工前，应进行标线车自动行驶试验",true,{"key":16,"text":17,"correct":18},"B","在正式划标线前，应保证路面表面清洁干燥",false,{"key":20,"text":21,"correct":18},"C","应根据设计图纸行放样",{"key":23,"text":24,"correct":18},"D","通过划线机的行驶速度控制好标线厚度","本题考查的是标线的施工技术要求。在标线工程正式开工前应进行实地试划试验。在正式划标线前，应首先清理路面，保证路面表面清洁干燥，然后根据设计图纸进行放样，并使用划线车进行划线。在进行划线时，应通过划线机的行驶速度控制好标线厚度。喷涂施工应在白天进行，雨天、风天、温度低于10℃时应暂时停止施工。喷涂标线时，应用交通安全措施，设置适当警告标志，阻止车辆及行人在作业区内通行，防止将涂料带出或形成车辙，直至标线充分干燥。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]