[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111072,786,1,"单选题","山岭隧道浅埋段施工中，严禁采用的施工方法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全断面开挖法",true,{"key":16,"text":17,"correct":18},"B","单侧壁导坑法",false,{"key":20,"text":21,"correct":18},"C","多台阶开挖法",{"key":23,"text":24,"correct":18},"D","双侧壁导坑法","根据围岩及周围环境条件，可优先采用单侧壁导坑法、双侧壁导坑法或留核心土开挖法；围岩的完整性较好时，可采用多台阶法开挖。严禁采用全断面法开挖。选项B、C、D均有利于隧道施工稳定与施工安全，全断面法开挖山岭隧道浅埋段易产生塌方。本题的正确项只能是“A.全断面开挖法”。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]