[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111043":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111043,786,1,"单选题","预应力筋张拉的实际伸长值△L（mm），可按下式计算△L=△L1+△L2，式中△L1表示从初应力至最大张拉力间的实测伸长值，△L2表示（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初应力以下的推算伸长值",true,{"key":16,"text":17,"correct":18},"B","超张拉伸长值",false,{"key":20,"text":21,"correct":18},"C","预应力损失伸长值",{"key":23,"text":24,"correct":18},"D","锚具变形伸长值","△L2表示初应力以下的推算伸长值（mm），可采用相邻级的伸长值。故选A",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]