[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111016,786,1,"单选题","关于钢筋混凝土梁桥施工时对于预拱度偏差防治的说法，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","支架基础应符合设计要求",false,{"key":16,"text":17,"correct":14},"B","预应力波纹管管道的安装定位应准确",{"key":19,"text":20,"correct":21},"C","控制预应力张拉的混凝土试块应采取标准养护",true,{"key":23,"text":24,"correct":14},"D","预制梁存梁时间不宜过长","主要考察的是预拱度偏差防治措施，预拱度偏差防治措施：(1)提高支架基础、支架及模板的施工质量，确保模板的标高无偏差；(2)加强施工控制，及时调整预拱度误差；(3)严格控制张拉时的混凝土强度，控制张拉的试块应与梁板同条件养护，对于预制梁还需控制混凝土的弹性模量；(4)要严格控制预应力筋在结构中的位置，波纹管的安装定位应准确；控制张拉时的应力值，按要求的时间持荷；(5)张拉千斤顶定期标定，钢绞线伸长值的计算应采用同批钢绞线弹性模量的实测值；(6)预制梁存梁时间不宜过长，控制预制梁与桥面系铺装的龄期差。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]