[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110999,786,1,"单选题","（2019年）关于填隙碎石基层施工技术要求的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","填隙碎石层上为薄沥青面层时，碾压后宜使集料的棱角外露3~5mm",false,{"key":16,"text":17,"correct":14},"B","填隙料应干燥",{"key":19,"text":20,"correct":21},"C","宜采用胶轮压路机静压，碾压时，表面集料间应留有空隙",true,{"key":23,"text":24,"correct":14},"D","填隙碎石基层未洒透层沥青或未铺封层时，不得开放交通","本题考查的是填隙碎石基层施工技术。填隙碎石施工时， 应符合下列规定： (1) 填隙料应干燥。 (2) 宜采用振动压路机碾压，碾压后，表面集料间的空隙应填满，但表面应看得见集料。填隙碎石层上为薄沥青面层时，宜使集料的棱角外露3~5mm。故选项C错误。 (3) 碾压后基层的固体体积率宜不小于85%，底基层的固体体积率宜不小于83%。 (4) 填隙碎石基层未洒透层沥青或未铺封层时，不得开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]