[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110995,786,1,"单选题","无机结合料稳定土基层摊铺完成后，紧跟摊铺机及时碾压的设备宜选用()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重型振动压路机",false,{"key":16,"text":17,"correct":14},"B","三轮压路机",{"key":19,"text":20,"correct":21},"C","轻型两轮压路机",true,{"key":23,"text":24,"correct":14},"D","轮胎压路机","(16)采用钢轮压路机初压时，宜采用双钢轮压路机稳压2-3遍，再用激振力大于35t的重型振动压路机、18-21t三轮压路机或25t以上的轮胎压路机继续碾压密实，最后采用双钢轮压路机碾压，消除轮迹。排除三轮、重型、轮胎。只能选C。在16教材中是有原话的",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]