[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110978,786,1,"单选题","（2019年）关于支撑渗沟施工的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支撑渗沟应分段间隔开挖",false,{"key":16,"text":17,"correct":18},"B","支撑渗沟侧壁宜设封闭层",true,{"key":20,"text":21,"correct":14},"C","支撑渗沟的基底宜埋入滑动面以下至少500mm",{"key":23,"text":24,"correct":14},"D","支撑渗沟的出水口宜设置端墙","本题考查的是支撑渗沟。支撑渗沟是用来支撑可能滑动不稳定土体或山坡，并排除在滑动面(滑动带)附近的地下水和疏干潮湿土体的一种地下排水设施。支撑渗沟的基底宜埋入滑动面以下至少500mm，排水坡度宜为2% ~4%。当滑动面较缓时，可做成台阶式支撑渗沟，台阶宽度宜大于2m。渗沟侧壁及顶面宜设反滤层。寒冷地区的渗沟出口应进行防冻处理。渗沟的出水口宜设置端墙。端墙内的出水口底标高，应高于地表排水沟常水位200mm以上，寒冷地区宜大于500mm。承接渗沟排水的排水沟应进行加固。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]