[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110974,786,1,"单选题","一般情况下，同一路段应先施工的路基地面排水设施是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","边沟",false,{"key":16,"text":17,"correct":14},"B","急流槽",{"key":19,"text":20,"correct":21},"C","截水沟",true,{"key":23,"text":24,"correct":14},"D","拦水带","此题主要是考察路基地面主要排水设施的施工顺序。题干中的关键词是“一般情况下”和“同一路段”，意味着按照常规施工的要求，如果在同一路段存在着以上四种路基排水设施的情况下，由于截水沟一般是设置在挖方段路堑的顶部，为了保证后续施工不受雨水的影响，所以一般情况下截水沟应先施工，与其他排水设施应衔接平顺。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]