[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110969,786,1,"单选题","石方填筑路堤的工艺流程中包括：①分层填筑；②检测签认；③振动碾压；④路基整修；⑤路基成型；⑥摊铺平整。其正确的顺序为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②①③⑥④⑤",false,{"key":16,"text":17,"correct":18},"B","①⑥③②⑤④",true,{"key":20,"text":21,"correct":14},"C","①⑥③④⑤②",{"key":23,"text":24,"correct":14},"D","④①⑥③②⑤","主要考察的是石方填筑路堤工艺流程，石方填筑路堤八道工艺流程是：施工准备、填料装运、分层填筑、摊铺平整、振动碾压、检测签认、路基成型、路基整修。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]