[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110962,786,1,"单选题","在非岩石地基上，填筑填石路堤前，应按设计要求设置（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过渡层",true,{"key":16,"text":17,"correct":18},"B","防水层",false,{"key":20,"text":21,"correct":18},"C","反滤层",{"key":23,"text":24,"correct":18},"D","整平层","在非岩石地基上，填筑填石路堤前，应设计要求设置过渡层。故选A",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]