[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110921,786,1,"单选题","当桥梁总体风险评估等级达到（）级及以上时，需将其中高风险的施工作业流动做专项风险评估。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅱ",false,{"key":16,"text":17,"correct":18},"B","Ⅲ",true,{"key":20,"text":21,"correct":14},"C","Ⅳ",{"key":23,"text":24,"correct":14},"D","Ⅴ","2020版教材P347 专项风险评估：当桥梁或隧道工程总体风险评估等级达到Ⅲ级(高度风险)及以上时，将其中高风险的施工作业活动(或施工区段)作为评估对象，根据其作业风险特点以及类似工程事故情况，进行风险源普查，并针对其中的重大风险源进行量化估测，提出相应的风险控制措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]