[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110894,786,1,"单选题","工程开工前，在业主（或监理）主持下，由设计单位向施工单位进行交桩。设计交桩的地点是在（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计院",false,{"key":16,"text":17,"correct":18},"B","现场",true,{"key":20,"text":21,"correct":14},"C","监理部",{"key":23,"text":24,"correct":14},"D","项目部","2020版教材P214 由建设单位组织，监理单位参加，设计单位对施工单位进行现场交接粧工作",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]