[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110889,786,1,"单选题","在安排公路进度计划中使用时间为横轴，以累计完成的工程量的百分数为纵轴的图形是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","“S”曲线",{"key":19,"text":20,"correct":21},"C","斜率图",true,{"key":23,"text":24,"correct":14},"D","网络圈","2020版教材P200 斜率图是以时间（月份）为横轴，以累计完成的工程量的百分数为纵轴，将7个分项工程的施工进度相应地用不同斜率表示的图表化曲（折）线。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]